Brookhaven Construction Update - The Grove Release Three
Welcome to your July construction update for The Grove Release Three.
Construction Progress
The Grove Release Three is progressing well, as our contractor SEE Civil continues to gain momentum on delivery of the stage.
The installation of water mains has commenced, and subgrade preparation is now complete, providing a solid foundation for our upcoming work. This sets the stage for installing the prime and asphalt concrete later this month.
Side drains and road crossings have wrapped up, and the completion of earthworks and boulder wall construction will shortly follow.
Valuations
Early site access for valuations, soil testing and site surveys will be available from Monday, 8 Monday.
See below for further details on how to arrange an appointment.
Settlement
We are pleased to advise that settlement remains on schedule to occur from September 2024. As always, our focus remains on quality and program as we work with our contractor to ensure we can settle your property as soon as possible. Should there be any change to this timing, our Customer Care team will be in contact with you. Congratulations again on your purchase; we look forward to welcoming you to the Brookhaven community.