Here’s the latest:

  • Detailed Excavation is complete for the basement 2 level.
  • The first section of the basement 2 level hydrostatic concrete slab has now been poured.
  • Preparations continue for the next basement slab concrete pour.
  • Installation of the waterproofing membrane to the B2-B1 walls in the southern zone are underway.
  • Basement walls will continue to follow the slab pours.

Our team is committed to delivering quality results and maintaining steady momentum. We’ll keep you informed of each new stage as we progress. Thank you for your continued support and interest in the project.

Settlement Update

At this stage, we anticipate the completion of Vela apartments to be in late 2026.

In the meantime, please do not hesitate to contact us on 13 86 88 if you have any questions or concerns.

Site Safety

We understand and share your growing interest and excitement as your new home begins to take shape. We are also highly committed to the safety of our purchasers and members of our construction team. Hence, we would like to remind you that at no time are any of our purchasers permitted to enter the construction site or fenced compounds, as doing so places you at risk of accident or injury.


Laura Struys Customer Care Coordinator Frasers Property Australia
Silvana Stojanovski Customer Care Coordinator Frasers Property Australia

See more construction updates on



You may also like