Shell Cove Construction Update - The Peninsula
Peninsula Aerial View December 2023
Welcome to the final construction update of 2023!
We’re pleased to keep you informed about how the project is progressing, give you insights into the construction process and ensure you’re up to date with the development of your new community.
Another project milestone was completed this week with asphalt surfacing completed for the Boollwarroo Parade road extension and the Shellharbour South Beach carpark. Line marking of Boollwarroo Parade and the carpark are scheduled to be complete in the next few weeks.
The sewer and servicing works are continuing with sewer approaching 50% completion and the sewer pumpstation being backfilled by Sydney Water. Electrical reticulation is almost finished with street lighting and pillar connections to take place in December and will continue into the new year.
The batter construction, tree planting and fencing at Keith Hockey Oval is now complete and the new grass along the outside are expected to establish over the next few weeks.
Settlement is anticipated to take place in late Quarter 1 of 2024.
New road and beach car parking on Boollwarroo Parade
New road extension on Boollwarroo Parade
The next construction update will be sent to you in the new year in February, 2024.
For now, on behalf of the Customer Care Team, we'd like to wish you a safe and happy holiday season!
Site Safety
We understand and share your growing interest and excitement as your new home begins to take shape. We are also highly committed to the safety of our purchasers and members of our construction team. Hence, we would like to remind you that at no time are any of our purchasers permitted to enter the construction site or fenced compounds, as doing so places you at risk of accident or injury.