Midtown Construction Update - SOUL Residences


13 April 2023

We are very pleased to bring you April's construction update for SOUL Residences at Midtown MacPark.

SOUL Residences

Another productive month onsite with the lift core now up to level 14-15 and the tower structure up to level 10.

Inside the building there are a variety of trades and activities underway. The high-level installation of services is complete up to level 6, wall installation on level 5, ceiling installation on level 3, wall setting and sanding on level 2, painting on level 1, and waterproofing to wet areas on the upper ground level.

We currently anticipate completion of Soul Residences to occur in the first quarter of 2024. This forecast is subject to construction progress, weather delays and receipt of title registration and the occupation certificate.

Midtown Site

Elsewhere on site the remaining roads are being completed, and this includes sewer, potable water and electrical infrastructure. Work continues on the Shrimpton's Creek bridge, with the deck being poured this month as well as the connection to Lyon Park Road.

Midtown Community

At the Midtown Community Garden there is an upcoming Composting and Worm Farming Workshop on 29 April. Check out the Midtown Community Garden Facebook page for more information @MidtownCommunityGarden, or register here: https://midtown-composting-workshop.eventbrite.com.au.

We will continue to update you every month as construction progresses, but in the meantime, if you have any questions, please do not hesitate to email customercareNSW@frasersproperty.com.au or call 13 86 88 or +612 9767 2297.

SOUL Residences (left)

SOUL Residences (right)

Shrimpton's Creek Bridge


Gavin Challis Customer Care Coordinator Frasers Property Australia