30 September 2022
MAC

As you can see in the photos below, there has been some excellent progress onsite. The core of the tower is now up to level 7-8, with the level 5 concrete pour commencing this week. The basement levels have been cleared and the installation of services is underway.

If you look closely at the first picture you can even see the façade of the building appearing behind the scaffold and construction fencing.

We are currently forecasting MAC Residences for completion and settlement by Quarter 4, 2023. This forecast is subject to construction progress, weather delays and receipt of title registration and occupation certificates.

We will continue to update you every month as construction progresses, but in the meantime, if you have any questions, please do not hesitate to email ProsperityCareNSW@frasersproperty.com.au or call 13 86 88 or +612 9767 2297.