myFrasersProperty 13 38 38
myFrasersProperty 13 38 38

Ed.Square Construction Update - Brooklyn Row - Block 1 (BE Homes)


14 February 2023

We are pleased to bring you an update on your home in Brooklyn Row Block 1.

Works have been progressing at a good pace onsite .

Lot 13046-13058: Roof install is now complete to the eastern wing, along with façade wrapping. The rough-in of services is continuing. The installation of cladding and internal linings is scheduled to commence now.

Lot 13059-13072: The western wing structure has now topped out and roof install has commenced. This has seen rough-in of services commence with façade works due commence late in the month.

Based on the current construction program, inspections and settlements forecast to occur in Quarter 3 2023.

The anticipated completion dates are based on the current program and are reviewed on a regular basis to ensure we deliver a quality outcome. From time to time, there will be movement in these dates to allow for unforeseeable events such as extreme weather.

If you have any queries about your home, please reach out to CustomerCareNSW@frasersproperty.com.au or call 13 86 88.

230203_Chelsea Pocket Block 1
Block 1 East

230203_Chelsea Pocket Block 1
Block 1 West


Brian Halpin Customer Care Coordinator Frasers Property Australia

See more construction updates on



You may also like